Featured Project: fp-TusherGreen River Tusher Diversion EWP Project

Client: USDA Natural Resource Conservation Service & State of Utah Department of Agriculture and Food

Bowen Collins & Associates (BC&A) completed design and construction management of the Green River Tusher Diversion Emergency Watershed Protection (EWP) Project. A new 880-foot long diversion dam was constructed to replace the original Tusher Diversion, a historic diversion dam that was originally constructed in 1913…more ›

Featured Project: fp-jordan-basinJordan Basin Water Reclamation Facility

Client: South Valley Sewer District

Bowen Collins & Associates completed Preliminary Planning, Design and Construction Management for the new Jordan Basin Water Reclamation Facility, owned and operated by the South Valley Sewer District. Planning for the new facility began in 2002. During the planning stages Bowen Co…more ›

Featured Project: fp-murdock-canalMurdock Canal Trail

Client:State of Utah Department of Water Resources

The State of Utah has been involved in regulating, assisting, and providing funding to local water agencies for decades. Recently, as the demand for water across the state has intensified, the State has come under criticism for not”>more ›

Featured Project: pepperwood-tank3 MG Water Tank Replacement Project

Client: Sandy City Public Utilities

BC&A designed a new 3.0 million gallon AWWA D115 post- tensioned, rectangular concrete tank to replace an existing tank that had been a continual maintenance problem for Sandy City since it was constructed more than 30 years ago…more ›

Featured Project: fp-aqueductSouthwest Aqueduct Reach 1

Client: Jordan Valley Water Conservancy District

BC&A completed the design and is currently providing construction management services for the Southwest Aqueduct Reach 1 Project (SWA-1). The design of the SWA-1 project included the evaluation of a new 66-inch Aqueduct that will parallel the existing 78-inch Jordan Aqueduct Reach…”>more ›

Featured Project: fp-southwestBear River Water Development Study

Client: State of Utah Department of Water Resources

Bowen Collins & Associates has been working with the State of Utah on the Bear River Pipeline Project to implement the Bear River Development Act. As Weber and Box Elder counties have grown over the last decade, the need to identify the route(s) for conveyance and storage facilities has intensified. Limited rights-of-way exist and many of those”>more ›

Featured Project: fp-terminalTerminal Reservoir Project

Client: Metropolitan Water District of Salt Lake & Sandy

The existing 40 MG Terminal Reservoir, owned and operated by the Metropolitan Water District of Salt Lake & Sandy (District), was constructed in 1950 and provides drinking water and fire protection storage for Salt Lake City and unincorporated Salt Lake County…more ›

Featured Project: fp-historicHistoric Utah Lake Pump Station Replacement Project

Client: Utah Lake Water Users Association

The historic Utah Lake Pump Station, once the largest pumping facility in the United States, was replaced in 2013 after over 100 years of reliable service.  The pump station is capable of conveying the entire flow of the Jordan River to satisfy the water demands of the Salt Lake Valley…more ›

Featured Project: fp-historicDry Creek Restoration Project

Client: Sandy City

BC&A completed the permitting, design, and construction management of a 700 linear foot channel realignment/restoration project for Sandy City. The project consisted of environmental permitting, the design of a box culvert at the intersection of Dry Creek and Monroe Street, channel design using bioengineering (designed to convey the 100 year storm), and landscape restoration….more ›