Summit County, Utah
Fisher Ranch WTP
Client: Jordanelle Special Services District
Jordanelle Special Service District contracted with BC&A to perform the design of a new surface water treatment plant taking raw water from the Provo River just downstream of Jordanelle Reservoir. The design portion included the initial treatment evaluation study, water quality testing programs, 3 months of pilot testing, budgetary planning, preliminary design, and final design. The current phase of the project is to construct 4 MGD worth of treatment on the site using a conventional coagulation/sedimentation and filtration treatment approach. Future phases will expand the capacity in this facility to 8 MGD, and eventually 16 MGD in a future building. This facility also includes the pumps, piping, and equipment to pump up to 10,000 gpm to a nearby ski resort for snowmaking operations. Construction on the project began in March 2022 and is scheduled to be completed in September 2024.